The force majeure clause does not cover the event
A general clause may say nothing about notice, extension of time, costs or the duty to mitigate loss.
Surface the contract's notice periods, allocation of risk and possible conflicts of interpretation before a delay turns into a financial settlement.
A general clause may say nothing about notice, extension of time, costs or the duty to mitigate loss.
Rights can be weakened when the contract's formal and time requirements are not followed through the project.
Differing provisions in the main contract and the subcontract can leave the contractor with liability it cannot pass on.
This is a constructed example that shows the format. It is not an assessment of an actual case.
«Does this force majeure clause entitle the contractor to both an extension of time and recovery of additional costs when the port is closed?»
Preliminary assessment: the clause has to be read word for word. Extension of time and cost recovery are separate questions, and a right to one does not automatically give a right to the other. The analysis would check the definition of the event, foreseeability, causation, the notice period and mitigation before drawing a conclusion.
Kilde: Norwegian Contracts Act section 36 and the agreed force majeure clauseAnd what the analysis extracts from each of them.
Notice periods, the variation procedure, the programme, liquidated damages and final account.
Whether notice was given in time and in the right form, and what is actually claimed: time, money or both.
Whether the terms mirror the main contract, or whether risk stops with the contractor itself.
The dates that decide whether a claim was notified in time.
Definition of the event, duty to notify, extension of time, cost recovery and mitigation.
Vi oppgir ikke hvor ofte hver enkelt feil forekommer — vi har ikke grunnlag for slike tall. Dette er kontrollene analysen faktisk kjører på dokumentene over.
A right to an extension of time does not automatically give a right to additional cost. The analysis splits the claim in two and answers each.
Notice periods are read out of the contract and held against the dates in minutes and correspondence.
Provisions that cannot be passed down the chain are flagged as risk the contractor carries itself.
A check of whether the contract cuts off claims not brought within a given deadline, and what is then lost.
Utdraget under er konstruert for å vise formatet. Det er ikke hentet fra en kundes dokument.
"Where circumstances beyond the parties' control prevent performance, the contractor is entitled to an extension of time. Notice shall be given without undue delay."
The analysis answers that the clause covers time, not money, and that a claim for additional cost needs a different basis. It suggests wording that sets a countable notice period, and lists what has to be documented about the impediment.
The sample question is filled in automatically. You can change the facts before the analysis starts.
Justera is a decision-support tool that uses AI — not legal advice. Consult a qualified lawyer for binding assessments.